Well here is some info about the current state of production "slippage", obviously it does not apply to me.
Dear all,

Please find attached your weekly production update, direct from Andy Brice, Production Manager.


The current status of production builds against the planned start date is as follows:

Aero 8

Currently approx. 8 weeks behind planned production start week.

+8

Currently approx. 8 weeks behind planned production start week.

However with the delays factored into the plan by the start of week 38 production will then be only 2 weeks behind the planned production start week.

Roadster

Currently on plan.

+4

Currently on plan and building in week stated.

4/4

Currently on plan and building in week stated.

4 seater

Currently 1 week behind but on plan from week 36 and building in week stated.

3W

Currently approx. 3 weeks behind planned production start week.

However with the delays factored into the plan by the start of week 36 production will then be only 2 weeks behind the planned production start week.


I hope this helps!